In principle clearance from Ministry of Energy, Government of Karnataka for 6.0 MW Biomass based Power generation plant to set up at Humnabad, Bidar District. |
 |
Approval from High Level Committee of Single Window Agency – Karnataka Udyog Mitra for infrastructural developments |
 |
Approval from Karnataka Power Transmission Corporation Ltd, Bangalore for Evacuation of generated power to their Sub Station at Humnabad. |
 |
During November 2002 enhancement of Installed Capacity from 6.0 MW to 7.5 MW from Ministry of Energy, GOK |
 |
Subsequent approval from KPTCL for evacuation of additional capacity |
 |
Signing of Power Purchase Agreement with KPTCL |
 |
Selection of land – conducted resistivity investigation by NGRI for availability of water and paid advance to the land lord |
 |
GOK has approved to set up the plant in private lands. The company has gone for private land due to non-availability of sufficient water in the lands allotted by the Govt. |
 |
Approval received from Ministry of Energy GOK duly approving the change of Constitution of Company from Private Limited to PUBLIC LIMITED COMPANY. |